I borrowed a dremel from work and hollowed out the standpipe a little bit so that the pipe actually fit.

The box is mounted and the plumbing is now complete. The box is a little tilted because it is a really cheap POS. Were I doing it again, I would build my own box.

I have reading to do for tomorrow, so I didn't too much after getting this part done. I still have the exterior outlets to do, which is the last item before the walls can be finished. I have half days tomorrow and Thursday so I can hopefully get those in tomorrow. Then it is the remaining plumbing in the floor.